Russia Puts Off Bushehr NPP Launch Until Fall 2008

Ivan Istomin said his company could not assemble the key operating equipment for the plant due to the failure by third countries to supply the necessary components, and cited lack of Iran's funding as one of the reasons. "Suppliers no longer have confidence in the Bushehr project," he said.
by Staff Writers
Moscow (RIA Novosti) Jul 26, 2007
The Bushehr nuclear power plant in Iran cannot be completed by the fall of 2007 as suggested by Iranian authorities and will only be commissioned a year later, a Russian subcontractor said. Russia is building the $1-billion facility, Iran's first nuclear power plant, in the south of the country in accordance with a 1995 contract, and under UN supervision as Iran is under international scrutiny over its compliance with the nuclear non-proliferation regime.

"Today we can say with all certainty that it would be unrealistic to put Bushehr into operation this fall," Ivan Istomin, the head of the Energoprogress company, said dismissing a statement made earlier this month by Iran's Mahmoud Jafari, co-chairing the project, that the plant could be ready in three or four months.

"Even if Russia delivers the first portion of nuclear fuel to Bushehr tomorrow, it would be impossible to commission the facility in six months," Istomin said.

The project came under threat in February after Russia complained about shortfalls in funding. Moscow said Tehran had only covered 60% of the required funding by the fourth quarter of 2006, and had completely stopped payments in mid-January. Iran denied any funding problems and accused Russia of delays.

Istomin said his company could not assemble the key operating equipment for the plant due to the failure by third countries to supply the necessary components, and cited lack of Iran's funding as one of the reasons. "Suppliers no longer have confidence in the Bushehr project," he said.

The official said it would take six months to restore trust and agree on new supplies. "The real deadline for the physical launch of the power unit will therefore be put off until the fall of 2008," he said.

Source: RIA Novosti

Related Links
Nuclear Power News - Nuclear Science, Nuclear Technology
Powering The World in the 21st Century at Energy-Daily.com



Memory Foam Mattress Review
Newsletters :: SpaceDaily :: SpaceWar :: TerraDaily :: Energy Daily
XML Feeds :: Space News :: Earth News :: War News :: Solar Energy News


French Firm Could Build Shield Over Main Chernobyl Reactor
Kiev (RIA Novosti) Jul 26, 2007
Ukraine could sign a contract with a French firm in September to build a giant protective shield over a damaged reactor in Chernobyl, the scene of the world's worst nuclear disaster, the emergencies minister said Wednesday. "The Assembly of Chernobyl Shelter Fund Donors made a decision in London July 17 to give its approval to the contract to build the shelter with the Novarka concern, with a preliminary cost of 490 million euros (about $680 million)," Nestor Shufrych said.







  • Vizada Launches SkyFile Access For Better Mobile Satellite Data Transfer
  • Bringing Mobile Cellular Phones To The Skyways
  • Rockwell Collins And ARINC Sign Agreement For Broadband Offering
  • Academic Group Releases Plan To Share Power Over Internet Root Zone Keys

  • Spaceway 3 Is Delivered To The Spaceport For Its Mid-August Ariane 5 Launch
  • Russian Space Firm Signs 14 Deals For Commercial Rocket Launches
  • Sea Launch To Resume Zenit Launches In October
  • Russia Proton-M Booster Puts US Satellite Into Orbit

  • Steering Aircraft Clear Of Choppy Air
  • EAA AirVenture 2007
  • Sensors May Monitor Aircraft For Defects Continuously
  • Goodrich Contributes Technology For Environmentally-Friendly Engine Research Program

  • LockMart And Northrop Grumman TSAT Team Announces Partnership With Juniper Networks
  • Northrop Grumman Wins Production Contract For E-2D Advanced Hawkeye
  • Raytheon To Develop Next Generation DIB Architecture
  • ViaSat Wins Order In MIDS Tactical Network Terminal Lot 8 Award

  • UCF And Holochip Announce Global Licensing Agreement For Zoom Lens Patents
  • Nature's Secrets Yield New Adhesive Material
  • Smart Fabric Biosensors Will Monitor Respiration Rate And Body Temperature In Real Time
  • BAE Systems To Produce Field Programmable Gate Array For Space Use

  • New SIDC Commander Has The Wright Stuff
  • NASA Administrator Names Ryschkewitsch As New Chief Engineer
  • Hall Appoints Feeney To Top GOP Position On Space And Aeronautics Subcommittee
  • Dodgen Joins Northrop Grumman As Vice President Of Strategy For Missile Systems Business

  • DigitalGlobe Expands Commercial Imagery Distribution Network In Australia And New Zealand
  • DMCii Wins ESA Satellite Imaging Contract
  • Campaign Prepares For Future Land-Surface Monitoring
  • Envisat Captures Breath Of Volcano

  • First Lockheed Martin-Built GPS Satellite Marks 10 Years In Service
  • Nokia Makes Finding Yourself Faster With New A-GPS Service
  • Poplar Creek Installs ProLink ProStar GPS To Enhance Golfer Experience And Deliver Advertising Revenues
  • SANYO Easy Street Portable Navigation Systems Make Their Debut

  • The content herein, unless otherwise known to be public domain, are Copyright Space.TV Corporation. AFP and UPI Wire Stories are copyright Agence France-Presse and United Press International. ESA Portal Reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space.TV Corp on any Web page published or hosted by Space.TV Corp. Privacy Statement