NASA, Human Lunar Lander Companies Complete Key Artemis Milestone
by Agency Writers for NASA News
Washington DC (SPX) Oct 23, 2020

Concurrent with the base period, NASA is running an active federal procurement for the next phase of HLS development, Option A, which will determine which design(s) will be selected to continue development to flight. The three HLS base period contractors, having passed CBR, are the only eligible offerors for Option A. (stock illustration only)

NASA's Human Landing System (HLS) Program recently checked off a key milestone in its progress toward landing the first woman and the next man on the Moon by 2024. The HLS Program conducted Certification Baseline Reviews (CBR) with the three U.S. companies competing to provide landers that will deliver Artemis astronauts to the Moon. These virtual meetings were the culmination of critical work by NASA and the companies since NASA announced the base period selections in April.

Since then, NASA has worked closely with the Blue Origin-led team, Dynetics, and SpaceX to better understand their human landing system proposals and approach for the agency's Artemis program. The primary purpose of the CBRs was to finalize the functional and performance requirements for the companies' landing system designs, confirm the standards to be applied to lander development, establish the baseline designs, schedules, and management plans for HLS contract execution and human spaceflight certification. Dr. Lisa Watson-Morgan, the HLS program manager at NASA's Marshall Space Flight Center in Huntsville, Alabama, chaired the CBR board that approved the certification baseline for each contractor.

Seeking to leverage NASA's human spaceflight experience and the commercial sector's speed and innovation, the agency specified a concept of operations and high-level requirements and standards but did not dictate approach or design, allowing the contractors to propose their own designs. This was a departure from NASA's traditional procurement approach of providing contractors with highly detailed specifications for building spacecraft hardware.

"We wanted to be as open as possible in our procurement approach, to accelerate the process and to encourage innovation," said Watson-Morgan. "It worked. Within one year, we were able to select three very different design solutions to accomplish the bold and challenging objective of sending astronauts to the lunar South Pole."

During the CBR meetings, NASA examined how each contractor has been proceeding with the design of their landing system, and NASA and the contractors confirmed the results of an intensive adjudication process that established design, construction, safety, and health and medical standards for each proposed landing system. Companies also provided development and testing schedules, identified top risks, and provided plans for safety and mission assurance, verification, validation, and certification.

The CBR is part of the base period for the three contracts. Running from May 2020 to February 2021, the base period is about mid-way through-the ideal time to conduct the CBR in the fast-paced development process, according to Watson-Morgan.

"With firm-fixed price contracts it is important to come to an agreement up front about how each contractor will proceed," she noted. "While NASA wants to be as flexible as possible to achieve success, late changes can be costly and add to schedule risk."

Next Steps to Land Artemis Astronauts on the Moon
Concurrent with the base period, NASA is running an active federal procurement for the next phase of HLS development, Option A, which will determine which design(s) will be selected to continue development to flight. The three HLS base period contractors, having passed CBR, are the only eligible offerors for Option A.

After receiving Option A proposals in late 2020, NASA plans to select up to two HLS Option A contracts near the end of the base period, providing a seamless transition to the next phase of HLS development that ultimately culminates in crewed demonstration missions to the lunar surface beginning with the Artemis III mission in 2024.

Through Artemis, NASA will land the first woman and next man on the Moon in 2024 and establish sustainable lunar surface exploration with our commercial and international partners by 2028. Artemis is the next step in human exploration and is a part of NASA's broader Moon to Mars strategy. Specifically, NASA's lunar operations will provide the agency with the experience and knowledge necessary to enable a historic human mission to Mars.

For more information about the Human Landing System Program, visit here


Related Links
Artemis at NASA
Mars News and Information at MarsDaily.com
Lunar Dreams and more


Thanks for being here;
We need your help. The SpaceDaily news network continues to grow but revenues have never been harder to maintain.

With the rise of Ad Blockers, and Facebook - our traditional revenue sources via quality network advertising continues to decline. And unlike so many other news sites, we don't have a paywall - with those annoying usernames and passwords.

Our news coverage takes time and effort to publish 365 days a year.

If you find our news sites informative and useful then please consider becoming a regular supporter or for now make a one off contribution.
SpaceDaily Contributor
$5 Billed Once


credit card or paypal
SpaceDaily Monthly Supporter
$5 Billed Monthly


paypal only


MOON DAILY
UK and NASA sign international agreement ahead of mission to the Moon
London, UK (SPX) Oct 14, 2020
NASA's Artemis programme aims to land the first woman and the next man on the Moon by 2024. Commercial and international partners will collaborate to achieve a sustainable presence on the lunar surface as a steppingstone to the first human mission to Mars. The UK will play a key role in this mission. Businesses across the UK will be involved in building the service module and habitation module of the Lunar Gateway, a new space station orbiting the moon, generating economic benefits and high-skille ... read more

Comment using your Disqus, Facebook, Google or Twitter login.



Share this article via these popular social media networks
del.icio.usdel.icio.us DiggDigg RedditReddit GoogleGoogle

MOON DAILY
Trouble in Orbit - 2021

UCI materials scientists discover design secrets of nearly indestructible insect

Scientists discover unusual materials properties at ultrahigh pressure

Bringing construction projects to the digital world

MOON DAILY
Air Force 'Orange Flag' exercise tests data transfers in combat

WGS-11+ Satellite Completes Preliminary Design Review

Defense Dept. awards $600M in contracts for 5G testing at five bases

Isotropic Systems and SES GS to trail next-gen multi-beam antenna technologies for US forces

MOON DAILY
MOON DAILY
China's self-developed BDS sees thriving applications

GPS-enabled decoy eggs may help track, catch sea turtle egg traffickers

Fourth GPS 3 Satellite Encapsulated Ahead of Launch

Government to explore new ways of delivering 'sat nav' for the UK

MOON DAILY
Wake Island Airfield undergoes $87M upgrade; Ceremony marks end of Marines' 'Tomcats'

Cathay Pacific to cut thousands of jobs, close subsidiary airline

Cathay Pacific to cut workforce by nearly a quarter

Fairchild, Shaw and Ellsworth AFBs make productivity gains

MOON DAILY
Researchers discover a uniquely quantum effect in erasing information

SK Hynix in $9 bn deal for Intel's flash memory chip business

SK Hynix in $9 bn deal for Intel's flash memory chip business

Researching the chips of the future

MOON DAILY
Predicting tornadoes on UK cold fronts for the first time

ICEYE shares nearly 18,000 satellite image archive under Creative Commons License

Serco Europe launches space research incubator in Italy

Two US satellites fail to enter orbit due to abnormal situation: Reports

MOON DAILY
Air pollution costs Europe cities $190bn a year: analysis

Pioneering LADAR system aims to revolutionize marine plastic detection

Bottle-fed babies ingest 'millions' of microplastics: study

Ancient trash heaps in Israel show waste management changes among settlements









The content herein, unless otherwise known to be public domain, are Copyright 1995-2024 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. All articles labeled "by Staff Writers" include reports supplied to Space Media Network by industry news wires, PR agencies, corporate press officers and the like. Such articles are individually curated and edited by Space Media Network staff on the basis of the report's information value to our industry and professional readership. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. General Data Protection Regulation (GDPR) Statement Our advertisers use various cookies and the like to deliver the best ad banner available at one time. All network advertising suppliers have GDPR policies (Legitimate Interest) that conform with EU regulations for data collection. By using our websites you consent to cookie based advertising. If you do not agree with this then you must stop using the websites from May 25, 2018. Privacy Statement. Additional information can be found here at About Us.